Foundation, Stem-wall, & Slab
This is the result of the 'fill' being placed as shown earlier. The beginning of the 'forms' for the footers and foundation.
Footers and foundation complete.
This is the result of the 'fill' being placed as shown earlier. The beginning of the 'forms' for the footers and foundation.
Footers and foundation complete.
We signed our construction contract in early August 2017. When our contractor went to get a permit, we (and he) were shocked that our land was in an 'Eagle Protection Zone'. This would not allow any 'outside' work to be performed between 10/1 and April of the next year. This called for a big decision about whether we should proceed this year or wait until next. Our contractor thought he could get it 'dried in' by 10/1 (many knowledgeable people were skeptical). We gave the go ahead, thankfully he had the roof on by October 1st-ish.